Before operating the double-conversion water tank wire drawing machine, it is necessary to debug first. First of all, you need to debug the host part. The specific content is to set the functions defined by all the terminals. Then debug the slave part. In fact, the debugging work of the double-conversion water tank type wire drawing machines can be divided into two steps.

 

The first step is to adjust the feedforward frequency of the double-conversion water tank wire drawing machine, and pay attention to adjust the keyboard potentiometer of the main machine to the minimum value. At this time, you should check whether the value of the feedforward frequency of the slave is zero. If the displayed value is not zero, then the slave's C-18 should be closely watched and its value entered into the slave's F-44. Then look again to see if the slave's feedforward frequency is zero when the host's potentiometer is modulated to the lowest value. Then adjust it to the maximum value to see if the feed forward frequency of the slave is consistent with the given frequency of the host.

 

The second step is to adjust the upper and lower limits of the pendulum. In this process, care must be taken to keep the physical and electrical positions of the pendulum consistent. When the parameters of the double-converter water tank type wire drawing machines inverter are set as required, the machine can be started.http://www.chinawiredrawingmachine.com/